What is PCBA processing first article inspection?
PCBA processing first piece inspection is a kind of error-proof mechanism to prevent batch PCBA accidents, which is to inspect, confirm and test the first product. First piece inspection is to detect problems affecting product quality in the production process as early as possible and to prevent batch defects or scrap. Only after all tests of the first piece test are passed, mass production can start, which can reduce the risk of wrong parts, lower the chance of errors, and effectively improve production quality.
First-part testing generally occurs in the following situations
1. The first time a new product is put on line
2. The beginning of each work shift or handover
3. Change of product type
4. Adjustment of equipment, jigs and fixtures, loading
5. Change of technical conditions, process methods and process parameters
6. After adopting new material or ECN material change
PCBA processing first piece inspection matters of attention
1. do protective measures, such as electrostatic protection, correct information.
2. whether the position, polarity, angle, etc. of the mounted components meet the requirements of technical documents.
3. whether the incoming quality of components is qualified, such as: component color, component size, positive and negative polarity, etc.
4. whether the welding quality of components meets the requirements of customers or related technical documents.
5. The inspector should make a mark on the first piece of qualified inspection according to the regulations, and keep it until the batch is completed.
6. the first inspection must be timely, so as not to reduce production efficiency.
7. the first piece without passing the inspection, shall not continue processing or operations
The purpose of the first piece inspection
1. The production process of the first piece inspection is mainly to prevent the product from appearing in batches of super poor, rework, scrap, it is a means of pre-emptive control of product production over, is an important method of product process quality control, is a proven and essential method to ensure product quality, improve economic efficiency.
2. The first inspection is to find out the factors affecting product quality in the production process as early as possible, to prevent the batch of bad or scrap.
3. The first piece of inspection before entering formal production, mainly to prevent the occurrence of batch of non-conforming products.
4. Long-term practical experience has proved that the first inspection system is an early detection of problems, to prevent the product batch scrap of effective measures. Through the first inspection, systematic reasons such as serious wear and tear of fixtures or wrong installation and positioning, poor accuracy of measuring instruments, wrong drawings, wrong feeding or formulation can be found, so that corrective or improvement measures can be taken to prevent the occurrence of batch nonconforming products.
Mechanism of PCBA processing first piece inspection
1. Self-inspection: Engineers conduct self-inspection of the first product they produce, mainly led by field engineers. The engineer can carry out self-inspection according to the above confirmed information, and the focus is on the direction of the components and the placement effect.
2. Mutual inspection: After the engineer inspection to the operator for mutual inspection, the focus is to check the BOM and drawings, there is no missing material and less material, etc., found objections immediately notify the production engineer to solve.
3. full inspection: after passing the full inspection sent to the quality inspection personnel, the general use of multimeter or ECR bridge, the scale of the factory basically use the bridge, the focus is on component measurement value, component orientation. If there are BGA devices need to use X-ray inspection to determine the internal soldering effect of the tin ball. According to the customer's original BOM, special processing requirements, samples and other product inspection to confirm whether the production of the first part of the customer's requirements, whether the product meets the requirements of the production technology documents to make a decision, while the production conditions and process parameters can be mass production of qualified products to make an evaluation. For the "three inspections" qualified PCBA samples are retained until the end of batch production.
4. The basis of the three-check system is the first part, and the first part comparison standard is the sample and the guidance document agreed by the factory and the customer in advance. The correctness of the sample includes the correctness of the material and the correctness of the soldering. The consistency of the customer's guidance documents and samples takes precedence over the documents, and in the absence of documents, the samples prevail. At any time, this basic principle can be followed, which is a protection for the foundry and a responsibility to the customer, with the aim of ensuring and improving the physical quality and avoiding quality losses due to mistakes on both sides.